What happened?
On July 9, 2026, the Logroño datacenter experienced a cascading power and cooling failure impacting customer workloads and services. The incident began at 21:59 CEST and required on-site manual intervention to restore service. Full power was restored at 23:05 CEST; complete service normalization concluded at 09:22 CEST on July 10.
No customer data loss has been identified.
How was this possible? (Root Cause)
The outage was caused by a single electrical fault that triggered a cascading sequence of automated safety responses.
At 21:59 CEST, a residual current device (RCD breaker D1) in the high-voltage control cabinet tripped. At this point, no visible outage occurred. However, the trip silently disabled the generator control system - the generators lost visibility of their circuit breakers and were no longer able to start automatically. The facility appeared fully operational, but its backup power capability was gone.
23 minutes later, at 22:22 CEST, the 66 kV high-voltage grid supply failed. The protection system detected overcurrent and initiated an automatic safety shutdown - a designed safety response, not a malfunction. Because the generators had been silently disabled since 21:59, they were unable to take over the load. All UPS systems switched to battery mode, protecting the workload throughout. However, as cooling infrastructure is not UPS-backed, all chillers and CRAH units lost power immediately.
Manual intervention by on-site staff restored grid power at 22:50 CEST. At 23:05 CEST, all generators were reset and the transformer breaker was closed, fully restoring power to the facility. The sequential service recovery process then began.
The exact cause of the initial D1 trip is still under investigation by our electrical engineering team and an external vendor performing forensic analysis on-site.
What we are doing to prevent recurrence
The investigation has already identified the architectural root cause: a single RCD breaker acting as a shared upstream dependency for both the generator control system and the high-voltage protection system. The following measures are being implemented:
Already completed
Short-term - within 4 weeks
Structural
Closing remarks
Despite the resilience measures already in place, service disruption could not be completely avoided during this event. The cascading nature of the failure - where a single circuit trip silently disabled backup power capability before the grid failure occurred - is a serious architectural finding, and we have moved immediately to eliminate that dependency.
On July 13, 2026, our infrastructure was put to a real-world test during a scheduled Iberdrola maintenance shutdown. All systems performed as designed. We are confident that the corrective actions taken are effective.
We recognize the impact this had on customers relying on our services and are committed to closing all identified action items with urgency and transparency.